Current Site Activity

Exchange 55 Progress

  • Asbestos abatement and demolition are ongoing
    • Asbestos removal is approximately 52% complete
    • Demolition is approximately 28% complete
      • North end of the site
        • The following structures have been successfully demolished and processed:
          • Elevated fly ash collection tank
          • Vertical water storage tanks
          • Storage structure
          • Fly ash electrical control building
          • Fly ash building
          • Small storage structure
          • Emergency services building
          • Upper and lower leg of North conveyor
        • South end of the site
          • The following structures have been successfully demolished and processed:
            • Vehicle repair building
            • Pulverize transformer and power support building
            • Electrical switch and controls
            • Maintenance building and internal transformers
            • Material storage structures
            • Conveyor direction transfer building
            • Marine conveyor
            • Maintenance building
            • Tank support and pump structure
            • Vehicle storage facility
            • Auxiliary generator building
            • Southerly switch yard
            • Elevated transformer house
            • South elevated conveyor
            • Transformer courtyard
            • Elevated switch relay deck

Updated March 25, 2019